The 2160 Hills Ave Industrial Paving Project involved a 2-inch mill and pave of the entire parking lot, along with the creation of a new parking layout. A total of 336 tons of 9.5mm asphalt was used for the project. The entire scope of work was completed in one day. A unique aspect of the project was the design of a new striping layout that added six additional parking stalls for the customer, including one ADA van accessible space.