2150 Boggs Road – Utility Repair

This project involved utility repair work, including the installation of graded aggregate base (GAB) and asphalt topping. A total of 18 tons of asphalt topping and 4 tons of 8-inch GAB were used to cover an area of 45 square yards. The project was completed in a single day. This undertaking was particularly unique due […]

Village Green Shopping Center Mill & Pave Project

The project at Village Green Shopping Center involved a 2-inch mill and pave of 45,345 square yards of asphalt parking lot, along with restriping that spanned 78,167 lineal feet. The project required 5,145 tons of asphalt and was executed in 13 distinct phases, which included milling, paving, and restriping each section before progressing to the […]

Legacy at Jones Farm Sealcoat Project

The project at Legacy at Jones Farm involved seal coating a total of 274,500 square feet of asphalt and restriping an apartment complex, requiring 5,500 gallons of asphalt sealcoat. Initially planned for a duration of seven days, the project was successfully completed in just five days. Located in Alabama, this project posed unique challenges due […]

Green Park South Road Resurfacing Project

The Green Park South Community Resurfacing project involved a 3-inch mill and pave of 9,085 square yards of asphalt roads throughout the community, along with the reconstruction of nine asphalt speed bumps. The project utilized approximately 1,200 tons of 12.5mm asphalt and was executed in three phases to ensure efficient completion and minimal disruption to […]

Goodwill (Snellville) Asphalt Resurfacing Project

The parking lot improvement project at Goodwill in Snellville involved a 2-inch Permaflex mill and pave overlay covering an area of 4,465 square yards. The scope of work included balancing the milling and paving processes to ensure the entire parking lot was resurfaced efficiently while keeping Goodwill fully operational throughout the project. The total project […]

2160 Hills Avenue Industrial Paving Project

The 2160 Hills Ave Industrial Paving Project involved a 2-inch mill and pave of the entire parking lot, along with the creation of a new parking layout. A total of 336 tons of 9.5mm asphalt was used for the project. The entire scope of work was completed in one day. A unique aspect of the […]

Five Benefits of Atlanta Parking Lot Milling
City of Peachtree Corners Street Resurfacing

The City of Peachtree Corners Street Resurfacing Project involved resurfacing 38 city streets across 11 subdivisions, with work including milling, patching, OGI (Permaflex), topping, and Full Depth Reclamation (FDR). The contract amount was $3 million, and the project was completed within three months. The quantities of materials used included 2,250 tons of OGI (Permaflex), 9,150 […]

Best Practices In Municipal Asphalt Pavement Installation
2024 Lake Arrowhead Road Improvement Project

The 2024 Lake Arrowhead Road Improvement Project encompasses essential roadway enhancements, including soil cement stabilization, milling and patching of existing surfaces, asphalt overlay application, and edge striping. The project aims to enhance road safety and durability while minimizing disruption to local traffic. Key quantities involved in the project include 3,000 tons of asphalt, 295 tons […]